Latest on Yarramundi Reach Buoyed Course: Update from the NCA

,

Latest on Yarramundi Reach Buoyed Course: Update from the NCA

Please be advised as follows in regards to the status on the Yarramundi Reach Rowing Course as of Friday 23 September 2011:

Three personnel have been working on the project in the past week.
The 30 longitudinal cables, both the SS terminals and the points for the buoys and weights where the O rings are to be attached are all complete and have been made up under tension.
The laterals will be worked on next.
Ian Dickinson has advised that little work will occur this week but has confirmed that works are still on schedule.